Accuracy is essential as the basis for any project. Sound decisions that will ensure the success of a project are reliant on accurate survey data at the start as well as throughout the project. This is why we are dedicated to providing the best surveying services using the best equipment available for the job. Selecting the right surveyor for a project can ultimately effect its successful outcome.

Here are some of our some recent accomplishments:

Australia Pacific LNG
Curtis Island
Leighton Contractors
October 2014-December 2014

The Project
Construction and commissioning of the Permanent Buildings, heavy duty pavements, road pavements, services and stockpile remediation (asbestos).

Australia Pacific LNG
Reedy Creek and Condabri Water Treatment Facilities
Leightons Contractors
May 2013 to Oct 2014

The Project
Construction of Water Treatment Facilities in south western Queensland
The project included large scale brine ponds, effluent ponds and buffer ponds. Also
included was surveying for the construction of roads, drainage HDPE pipework, electrical
conduit network, concrete structures plus mechanical installation, set out, redesign,
conformance and as constructed.

Broadmeadow Mine BSO Project, CQ
Leighton Contractors
April 2011 – April 2013

The Project
The BSO Project was the conversion of an Open Cut Pit to an underground mining operation involving:

  • the removal and placement of 8 million cubic meters of rock and soil
  • low wall and high wall works
  • 2.5 kilometer conveyor
  • 6 km levee wall 5m high with a key down to 25m below ground level
  • construction of a major rock filter buttress to stop inundation from Eureka Creek
Yarrabee Coal Mine CQ
AE Civil and Mining
Feb 2009 – Feb 2011

Upgrade existing Coal Haul Road

Boonal Joint Venture CQ
AE Civil and Mining
Feb 2009 – Feb 2011

The Project
Upgrade a Coal Loadout facility

Oaky Creek Mine CQ
AE Civil and Mining

The Project
Survey of 3 sites within the mine lease for future upgrades

Stanwell Power Station CQ
AE Civil and Mining
Feb 2009 – 2011

The Project
Expansion of existing Ash Dam

South East QLD Correction Precint Project, Gatton,
AE Civil and Mining
Nov 2007 – Nov 2009

The Project
Construction of the SEQ Correctional Centre – a large earthworks project involving
2 million m3 of earthworks, drainage, dams, concrete channels and cascade drainage structures.

Leighton Contractors

– Inner City Bypass
– RAAF Base Extension Stage 2, Amberley
– Goonyella – Abbot Point Expansion Project (Coal Connect Alliance)
– Australian Super Hornet Project, RAAF Base Amberley
– QUT Carseldine Expansion
– M1 Motorway
– Gunpowder Mine Expansion Project
– Eungella-Moranbah Pipeline

John Holland Pty Ltd
– Gold Coast Desalination Plant
– Port of Gladstone
– Brisbane Water Enviro Alliance Oxley

Bassett
– Oakey Aviation Base Fuel farm Upgrade Project

Lend Lease (formerly Abigroup)
– Pimpama Coomera master water plan implementation
– Gold Coast Pumps and Pipes